COVID-19: Renegotiation in case of an upheaval in the contract economy

 

The exceptional circumstances resulting from the measures imposed in order to prevent the propagation of COVID-19 may make it excessively onerous for companies to fulfil their contractual obligations, without, however, preventing them from doing so.

In order to cope, statutory and contractual provisions allow debtors to request the renegociation of their engagements.

If it has been provided from the beginning, a hardship clause must be implemented by the aggrieved contracting party (I.). Where no such clause exists, the debtor may benefit from the general legal provision of revision for unforeseen circumstances provided by article 1195 of the Civil Code (II.).

I. IMPLEMENTATION OF HARDSHIP CLAUSES

Hardship clauses (most often related to an event of an economic rigour liable to disrupt the economy of the contract[1]) are common in international contracts, in order to compensate the absence or inadequacy of a legal mechanism of revision for unforeseen circumstances[2].

These clauses usually oblige the contracting parties to renegotiate the contract in the event of unforeseeable events occurring after the conclusion of the contract, in which the injured party should not assume the risk[3], and render the performance of the contract particularly onerous.

Concerning the excessively onerous effect, the Court of Cassation seems to require the injured party to demonstrate, difficultly, a fundamental alteration of the balance of the respective prestations[4]. On a case-by-case basis, and depending on the prestation concerned, the coronavirus crisis could lead to such an alteration.

Hardship clauses differ from clauses that provide an automatic mechanism to adapt contractual stipulations, usually with reference to indexes determined in advance by the parties (e.g. indexation clauses that take into account measurable events, whether or not the origin of these events is foreseeable).

Indeed, the hardship clause does not automatically set the new contractual stipulations that will apply once the triggering event occurs. It is always preferable for the parties to have, as far as possible, contractually specified the factors for implementing the clause and the conditions of renegociation ; in particular, this will be done by specifying in the contract which clauses may be modified, if necessary within limitations, or by allowing the intervention of a third party whose mission must be precisely defined beforehand[5].

If the renegotiation is successful, the contract remains in force with the amendments made by the parties. If the discussions fail, the contract should in principle continue to produce its effects under the original conditions, unless the circumstances which led to the renegotiation can be analysed as a genuine case of force majeure which prevents its performance or unless a claim can be brought before the courts ; it will be the case if the contractual clause provides specific obligations (such as the obligation for each party to submit proposals for new clauses balanced for each party) or the possibility to seek judicial redress in the absence of agreement between the parties. Some clauses even provide that the failure of the renegotiation will give the parties the right to terminate the contract.

Since the Contract Law reform in 2016, if the renegociation fails, a judicial review may be requested if the parties to a contract governed by French law have not excluded the application of Article 1195 of the Civil Code[6].

If the parties have excluded the application of Article 1195 of the Civil Code, the judge’s power will be limited to verifying that the conditions for hardship have been met and that the parties have effectively renegotiated the contract in good faith. The judge may terminate the contract or refer the parties to a final renegotiation and it will be up to him to sanction the prejudicial behaviour of a party[7].

 

[1]    L’obligation de renégociation du contrat, P. ACCAOUI LORFING, Revue de droit international et de droit comparé, 2015, n°2.

[2]    Cass. Com., 17 février 2015, n° 12-29.550 : https://www.doctrine.fr/d/CASS/2015/JURITEXT000030270329

[3]    JCl. Civil code, Contrats internationaux, M. SANTA CROCE, 30 avril 2018, n° 33 à 35.

[4]    Droit civil, Les obligations, F. TERRE, 2019.

[5]    L’obligation de renégociation du contrat, P. ACCAOUI LORFING, Revue de droit international et de droit comparé, 2015, n°2.

[6]    Causes d’exonération en matière de responsabilité contractuelle, B. RAJOT, 9 mai 2019.

[7]    Hardship et révision des contrats, Quelle méthode au service d’une harmonisation des droits ?, M. MEKKI, JCP G n° 49, 6 décembre 2010, doctr. 1219.

II. LE DISPOSITIF LÉGAL DE DROIT COMMUN DE RÉVISION POUR IMPRÉVISION

The new Article 1195 of the Civil Code, resulting from the Ordinance dated 10 February 2016 reforming Contract Law and applicable to contracts signed as from October 2016, now lays down a general rule for dealing with unforeseen situations (i.).

However, this text leaves a certain number of special pre-existing statutory provisions, which in principle exclude the application of Article 1195 of the Civil Code (ii.).

 

(i.) Article 1195 of Civil Code:

« If a change in circumstances unforeseeable at the time of the conclusion of the contract makes performance excessively onerous for a party who had not agreed to assume the risk, that party may request the other party to renegotiate the contract. It shall continue to perform its obligations during the renegotiation.

In the event of refusal or failure to renegotiate, the parties may agree to terminate the contract, on the date and under the conditions they determine, or request by mutual agreement that the judge proceed to adapt it. If no agreement is reached within a reasonable period of time, the court may, at the request of one of the parties, revise or terminate the contract, on the date and under the conditions it shall determine. »

In preamble, it should be pointed out that Article 1195 of the Civil Code establishes a suppletive mechanism which leaves a large place for clauses and agreements contrary to its provisions[8] and would preclude the application of Article 1195 of the Civil Code within the limits of the texts penalising unfair terms such as those which would transfer to one of the parties the essential risks of a change of circumstances and would entail unreasonable consequences for that party  [9].

Although the text provides that the injured contracting party may have agreed to assume the risk which render the performance of his obligations excessively onerous, part of the doctrine considers that it is uncertain whether the parties can validly waive purely and simply the provisions of Article 1195 of the Civil Code, awaiting a decision of the Court of Cassation on this point[10].

Les conditions de prise en compte de l’imprévision sont les suivantes :

  • Article 1195 of the Civil Code applies to all contracts concluded since the 1st of October 2016 ;
  • the cause of the disruption must be an objective change of circumstances ;

–  moment of change: the change in circumstances must have been unforeseeable for the parties at the time of the conclusion of the contract and the imbalances must therefore result from elements occurring after its conclusion; with regard to the coronavirus crisis, it could be discussed when this crisis (and its effects on the economy and the performance of contracts) became foreseeable for the parties: 31 December 2019 with the first alert in China? the end of January 2020 with the start of containment in that same country? March 12, 2020, when the French Government announced the shutdown of schools?…

–  origin of the change: the imbalances must have causes external to the affected party[11]. For the coronavirus crisis, it will be difficult to consider that this requirement is not met, except in exceptional circumstances (specific negligence by one party…).

–  nature of the change: the notion is broad enough to refer to a sudden, brutal event, or not. For the coronavirus crisis, change should be characterisable in many contractual situations (due to restrictions on movement, sick staff or staff forced to look after their children, supply difficulties for certain industries, etc.).

–  the nature of the distortion: :  the performance of the obligations by the contracting party, although possible, must have become excessively onerous; in the case of the coronavirus, only a case-by-case assessment will make it possible to evaluate whether or not this requirement is met.

–  the unpredictability of the change of circumstances at the time of conclusion: Article 1195 of the Civil Code is only applicable in the event of an occurrence that the parties were unable to reasonably take into account at the time of the contract conclusion[12] ; although it is difficult to claim that the coronavirus crisis (and its effects) was foreseeable, at least before the beginning of 2020, some might try to evoke the words of Bill Gates (dated 2015) or a 2009 CIA report that warned on the risks of a pandemic and a contagious virus coming from China…

–  lack of assumption of risk:   the aggrieved party may not have accepted to assume the risk which makes the performance of the contract excessively onerous. Particular attention should be paid to the content of the contractual provisions, as some contractors have learned from previous epidemics or pandemics by introducing standard clauses for the acceptance by their co-contractor of similar risks.

 

The way in which the situation will be dealt with:

  • the precondition of a request for renegotiation by the injured party to its co-contractor: if the text indicates that it “may” request a renegotiation of the contract from its co-contractor, it is an obligation if the injured party then wants to request a judicial review of the contract, which the judge can only grant in the event of refusal or failure of a renegotiation. The refusal to renegotiate engages the responsibility of the recalcitrant party, the failure of the renegotiation implies that it was carried out in accordance with the requirements of good faith. Finally, the parties may decide by mutual agreement to terminate the contract  [13].
  • if there is no agreement between the parties within a reasonable period of time, the judge may then, without any obligation of hierarchy,
    –  amend the contract : in this area, the power of the court seems a priori to be unlimited, awaiting decision of the Court of Cassation; however, it is possible to think that the court will concentrate on amendments which make the performance of the contract less “excessively onerous“, without assuming the right to rebalance a contract which would have been, from its origin, significantly to the advantage of one of the parties;
    –  or, terminate the contract: as the power of the judge to terminate the contract is drafted in general terms, it could be possible for the courts to decide freely on the date of termination of the contract (on the day of the decision, the day of occurrence of the change, after their decision in order to give notice, …), to fix the conditions of termination or cancellation and to allocate damages to the party who has benefited from the change of circumstances [14].

 

(ii.) The pre-existing statutory provisions:

Article 1105 of the Civil Code provides that “the general rules apply unless special rules apply“.

Certain provisions exclude the revision of the unbalanced contract such as the following articles:

  • Article 1793 of the Civil Code, applying to contracts for the construction of a building at a fixed price according to a plan agreed with the owner of the land, which provides that the builder may not request any price increase “either under the pretext of an increase in labour or materials, or under the pretext of changes or increases made to the plan, unless such changes or increases have been authorized in writing and the new price has been agreed to by the owner”  [15].

It should be noted, however, that the Court of Cassation [16] has already conceded that the judge could, even in the absence of written authorization, grant a price supplement if the requested amendments resulted in a “disruption in the economy of the contract” ;

  • Article L.211-40-1 of the Monetary and Financial Code, which excludes the application of Article 1195 of the Civil Code “to obligations arising from transactions in the securities and financial contracts mentioned in I to III of Article L.211-1” of the said Code.

In addition, there are special provisions for a revision of a contract that would become “unbalanced“; in particular in the following cases:

  • life annuities;
  • certain rents for commercial, rural and residential tenancies;
  • contracts for transfer of copyright (Article L. 131-5 of the Intellectual Property Code);
  • the cash balance due from a co-sharer (Article 828 of the Civil Code).

 

Therefore, with regard to exceptional situations, the possibility of renegotiating contractual agreements appears particularly useful and needs to be studied on a case-by-case basis, particularly in the context of the coronavirus crisis.

However, the performance of agreements (even if costly) must be pursued during the renegotiation and the mechanism of Article 1195 of the Civil Code gives important powers to the judge, reducing the parties’ capacity to control the future of their contractual relationship.

Finally, as this option comes from a recent provision (Ordinance dated 10 February 2016), it does not, as it stands, offer any hindsight on its practice by the courts; the coronavirus crisis could constitute a real test for the parties and for the courts…

 

[8]    Répertoire de droit civil, Imprévision, P. ANCEL, 2017, n° 56 et 95.

[9]    L’article 1171 du Code civil prévoit à cet égard que « dans un contrat d’adhésion, toute clause non négociable, déterminé à l’avance par l’une des parties, qui crée un déséquilibre significatif entre les droits et obligations des parties au contrat est réputée non écrite ».

[10]    Répertoire de droit civil, Imprévision, P. ANCEL, 2017, n° 95

[11]    Répertoire de droit civil, Imprévision, P. ANCEL, 2017, n° 70.

[12]  Coronavirus (COVID-19) : Faut-il préférer l’imprévision à la force majeure ?, X. AZAIS, Village de la justice, 19 mars 2020.

[13]    L’article 1195 du Code civil français ou la révision pour imprévision en droit privé français à la lumière du droit comparé, P. ACCAOUI LORFING, RDAI/IBLJ, n°5, 2018.

[14]    Pour un exemple de résiliation consécutive à un refus de renégocier, CA Paris, pôle 5 – ch. 11, 17 janv. 2020, n° 18/01078 : https://www.doctrine.fr/d/CA/Paris/2020/C2C014820AE9C5FAD6DD8

[15]    « L’article 1793 qui édicte des règles spéciales déroge aux règles générales de l’article 1195 précité » ; CA Douai, ch. 1 sect. 2, 23 janv. 2020, n° 19/01718 : https://www.doctrine.fr/d/CA/Douai/2020/C01C67E1C395BAEDC16C7

[16]    Cass. Civ. 3ème, 24 janvier 1990, n° 88-13.384 : https://www.doctrine.fr/d/CASS/1990/JURITEXT000007022754

Our last newsletters

Sanctions Against Russia. Recent Developments

On 23 February 2024 European Union and the United States introduced a new round of sanctions targeting Russia. The 13th package of European sanctions provides for new individual sanctions, sectoral sanctions, export restrictions. Additionally, EU added the United Kingdom to the list of partner countries for the iron and steel import restrictions. American sanctions include […]

Moscow Desk

+

Newsflash – Corporate – Venture Capital – French government announcements to support Innovative Startup Companies (JEI)

For the occasion of the French Tech’s 10th anniversary, new measures stemming from the  report of Parliament Member Paul Midy (for which Jeantet had been consulted) have been announced. These measures, which aim at supporting the French startup ecosystem, should be included in the next Finance Act for 2024. ► Doubling of companies eligible to […]

| CORPORATE – M&A – PRIVATE EQUITY

+

Russian Counter Measures. Recent Developments

On 23 August, the Russian Ministry of Finance partially lifted a ban for the payment of dividends to foreign shareholders in case such shareholders have invested in the Russian economy. On 8 August, the Russian President suspended certain provisions of double tax treaties. Suspended provisions include tax regime for dividends, real estate, business profit, etc […]

Moscow Desk

+

Sanctions Against Russia. Recent Developments

On 23 June 2023, the EU introduced 11th package of sanctions. It primarily focuses on measures that would prevent circumvention of sanctions. It also includes new import and export restrictions and individual designations. Switzerland has joined European Union in sanctions targeting entities and individuals and may join other sanctions within the 11th package in August. […]

Moscow Desk

+

Newsletter – Tax law

Read the Jeantet Newsletter dedicated to Tax Law, covering issues related to : Transactional taxation Group taxation International Taxation Taxation of LBO transactions Non-profit organizations For more information, please download the Newsletter.

Paris | TAX

+

Russian Counter Measures

On 25 April 2023 Russian President issued a decree establishing cases authorizing him to introduce the regime of external management of certain assets owned by foreign residents. Namely, under the decree, the President may establish the regime of external management, if Russia, or its entities and individuals become deprived or risk of being deprived of […]

Moscow Desk

+

Russian counter measures and measures aimed at business support. Recent developments

Special regime for transactions involving securities On 3 March 2023 Russian President issued Decree No. 138 establishing additional measures involving securities. Namely, the new Decree establishes a specific procedure for transactions / operations involving: shares of Russian joint-stock companies, sovereign bonds, bonds of a Russian issuer, held in collective safe custody of a Russian depository, […]

Moscow Desk

+

Sanctions against Russia. Recent developments (2 march 2023 update)

By the end of February, the EU, US and UK announced new rounds of sanctions, all of them including restrictions targeting prominent Russian financial institutions The EU package includes individual listings of Russian entities and individuals and additional exports restrictions. The US sanctions provide for sectoral sanctions targeting Russian mining and metals sector, as well […]

Moscow Desk

+

Russian counter measures. Recent developments ( 12 january 2023 update)

Governmental Commission on Foreign Investments revised rules on the sale of assets and the payment of dividends On 30 December 2022, Russian Governmental Subcommission of the Commission of the Ministry of Finance on Foreign Investments (the – Commission) published revised rules and criteria for authorization of the sale of assets in Russian companies involving persons […]

Moscow Desk

+

Sanctions against Russia. Recent Developments (21 December 2022 update)

This December, the EU introduced a series of restrictive measures targeting Russia. Council of the EU approved the ninth package of sanctions. Additionally, the European Commission proposed framework that would amend the Lisbon Treaty and harmonize criminalization of violation of sanctions at the level of the Union. Finally, the EU introduced a price cap for […]

Moscow Desk

+

Russian counter measures. Recent developments (21 December 2022 update)

Russia has adopted a series of new measures. Namely, the President introduced new restrictions concerning certain transactions involving credit organizations and joint-stock companies that are not credit organizations. The Russian Central Bank issued decision expanding the scope of application of type C accounts. Moreover, the Ministry of Finance issued clarifications on the scope of transactions […]

Moscow Desk

+